Skip to main content
Skyline

30 Nov 2026

Curtailment signals grid evolution in South Africa’s energy market, not failure.

Bernard Geldenhuys

Bernard Geldenhuys | Head of Energy Finance at Investec Corporate & Investment Banking

Energy curtailment is an accepted operational reality of a modernising power grid, not a sign of structural failure.

Oversupply dynamics

Curtailment graph

During the first half of 2026, South Africa's electricity grid experienced curtailment volumes that were approximately ten times higher than those recorded throughout 2025.

While these headline figures have raised concerns among market participants, the increase in curtailment does not necessarily indicate a failing power system.

Rather, it reflects the structural evolution of a grid transitioning towards higher levels of renewable energy penetration, a phenomenon that has long been observed and accommodated in mature international electricity markets.

The emergence of system-wide daytime oversupply stems from a convergence of macroeconomic, technical, and structural factors.

Weak economic growth has constrained electricity demand, particularly among energy-intensive industrial consumers. Several major smelting facilities have previously reduced operations in response to elevated electricity tariffs.

Although Eskom has introduced discounted tariffs of approximately 62c/kWh to encourage the return of certain industrial loads, the anticipated increase in demand has yet to fully materialise.

At the same time, significant growth in behind-the-meter (BTM) solar photovoltaic (PV) generation has materially reduced daytime grid demand. Investment in rooftop solar across residential, commercial, and industrial sectors has displaced substantial volumes of grid-supplied electricity during daylight hours, further contributing to midday generation surpluses.

 

The rise of BTM solar in South Africa

Up to 8,400 MW

Estimated BTM solar capacity

2,574 MW

BTM solar capacity in 2022

~190%

Growth since December 2022

 

The challenge created by rising daytime renewable generation is compounded by the relative inflexibility of Eskom's coal fleet. While fleet performance has improved materially in recent years, large baseload generating units cannot be rapidly cycled to accommodate short-term fluctuations in solar output.

Consequently, renewable generation, particularly solar PV, is increasingly being instructed by the National Transmission Company South Africa (NTCSA) to reduce output to preserve overall system stability.

 

Contractual mechanics and private market exposure

The commercial implications of curtailment depend heavily on the structure of the underlying Power Purchase Agreement (PPA).

Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) projects benefit from take-or-pay arrangements, under which deemed energy provisions protected project revenues by compensating generators for curtailed output.

However, more recently, the REIPPPP Bid Window 5 & 6 framework has shifted a portion of this risk back to project sponsors through a 5% uncompensated curtailment allowance, resulting in a direct project revenue impact.

The exposure faced by private wheeling projects operating under Distribution Connection and Use-of-System Agreements (DCUSAs) may be more pronounced. In many cases, private offtakers pay only for energy actually delivered, while curtailment relief is typically limited to time extensions that are themselves subject to contractual caps.

While these mechanisms may provide some support in the context of temporary curtailment events, they do little to address liquidity pressures where curtailment becomes structural or persists over an extended period.

To date, the NTCSA has generally adopted a practical approach under which private wheeling projects have effectively been treated as "do not curtail" facilities. However, the contractual position remains less certain. Although existing DCUSAs contain provisions suggesting that private projects would only be curtailed after other generation sources have been restricted, the drafting affords the system operator significant discretion.

 

 

Yudhvir Harrilal photo
Bernard Geldenhuys, Head of Energy Finance at Investec Corporate & Investment Banking

Private projects may remain legally exposed to curtailment risk, notwithstanding the limited practical experience of curtailment to date.

Learn more about Energy And Infrastructure Finance

Rethinking bankability - contractual and technical solutions

The emergence of curtailment as a material market consideration is likely to influence the way projects are financed and assessed by lenders.

Historically, many financing models implicitly assumed minimal curtailment risk. Going forward, lenders may increasingly incorporate explicit curtailment assumptions into base-case forecasts, debt sizing methodologies, or downside sensitivity analyses.

Part of the solution may be contractual. Sponsors and offtakers may consider mechanisms that preserve project economics where curtailment exceeds agreed thresholds, including tariff adjustment provisions or risk-sharing arrangements.

Alternatively, tariffs could incorporate an assumed level of curtailment from inception, with benefits shared between sponsors and offtakers if actual curtailment proves lower than forecast.

A second solution is technical. As renewable penetration grows, standalone solar projects may face increasing bankability challenges relative to hybrid renewable-plus-storage configurations.

Utility-scale Battery Energy Storage Systems (BESS) provide the flexibility to absorb surplus daytime generation and shift energy into higher-value evening periods. However, storage is not a complete solution in isolation. Where a battery is already forecast to operate at full charge under normal production assumptions, incremental curtailed energy may remain stranded.

The effectiveness of BESS as a curtailment mitigation tool therefore depends not only on its existence, but also on its sizing, operating strategy, forecasting assumptions, and the economics of battery cycling.

In practice, the most resilient projects are likely to combine both contractual and technical mitigation measures.

 

Get Focus insights straight to your inbox

* indicates required field.
Enter your name here *

This information is required

Minimum characters 1

This is a required field.

Enter your surname here *

This information is required

Minimum characters 1

This is a required field.

Enter your email address here *

This information is required

Minimum characters 1

Please enter a valid email address

Enter other service here

This information is required

Minimum characters 1

YYYY *

This information is required

Minimum characters 1

This is a required field

Please complete all required fields before sending.

Thank you

We look forward to sharing out of the ordinary insights with you

Capital structuring for the next era

Addressing curtailment risk will require greater alignment between developers, corporate offtakers, lenders, and the NTCSA, along with improved transparency regarding system constraints and dispatch priorities.

Projects may increasingly seek flexible offtake arrangements incorporating dynamic tariff structures or risk-sharing mechanisms that allocate curtailment impacts more equitably between project stakeholders. Combining extension-of-time provisions with appropriately designed tariff adjustment mechanisms could help preserve project liquidity where curtailment becomes a structural feature of the grid rather than a temporary operational event.

Hybridisation through utility-scale storage is also likely to become an increasingly important component of future project design.

Although the South African Wholesale Electricity Market (SAWEM) is expected to introduce mechanisms that provide greater price signals and potentially more sophisticated approaches to curtailment allocation and compensation, the final structure remains uncertain.

What is clear, however, is that curtailment should no longer be viewed as an exceptional event. It is increasingly becoming a feature of a power system undergoing a complex but necessary transition.

The projects best positioned to succeed will not be those that assume curtailment can be avoided entirely, but those that proactively allocate, manage, and price the risk as part of a sustainable long-term business model.

 

Get more Investec Insights

Previous
Previous